If you’re buying near central I-35 or a planned light rail line, here’s the short version: TxDOT’s $5.6 billion I-35 Capital Express Central project is under construction between US 290 East and SH 71/Ben White Boulevard, with completion expected in 2033, and Austin Light Rail Phase 1 is planned to open in 2033 on a 9.8-mile line from 38th Street on Guadalupe through downtown to South Congress and East Riverside. Both projects will shape daily routes, noise, and access near the corridors for years.
What I won’t do is tell you what either project will do to home prices. Nobody knows that, and I’d be guessing. What I can do is show you what the official schedules say, as of November 17, 2026, and how to check what’s planned near a specific address before you buy.
The I-35 Capital Express Central project
According to TxDOT, the Central project will:
- Add two non-tolled high-occupancy-vehicle (HOV) managed lanes in each direction from US 290 East to SH 71/Ben White Boulevard
- Lower the mainlanes from Airport Boulevard to Lady Bird Lake and remove the upper decks
- Add boulevard-style segments through downtown and improve transit connections
- Add more than 19 miles of new shared-use paths and 13 connections to the urban trail and bicycle network
TxDOT also lists new bicycle and pedestrian crossings at 4th Street, 55th Street/Capital Plaza, the Red Line at Airport Boulevard, Lady Bird Lake, and Woodland Avenue, plus a crossing at 41st Street. The City of Austin and UT are working with TxDOT on possible deck caps and stitches over the lowered highway, which the City and UT would fund to operate and maintain.
Construction started in October 2024 with the rebuild of the Martin Luther King Jr. Boulevard bridge. TxDOT expects construction along the whole corridor to be complete in 2033, weather permitting.
The schedule by segment
TxDOT’s technical schedule, last updated September 2, 2026, breaks the work into segments:
| Segment | Status | Start | End |
|---|---|---|---|
| MLK Bridge | In construction | 2024 | 2026 |
| Lady Bird Lake (Holly Street to Ben White Boulevard) | In construction | 2024 | 2033 |
| Drainage tunnels | In construction | 2025 | 2029 |
| Pump station | In construction | 2025 | 2030 |
| University advance construction | Letting November 2026 | 2027 | 2032 |
| Downtown advance construction | Letting February 2027 | 2027 | 2033 |
| University (US 290 East to MLK) | Letting September 2028 | 2029 | 2033 |
| Downtown (MLK to Holly Street) | Letting September 2029 | 2030 | 2033 |
“Letting” is when TxDOT awards a construction contract. So if you’re looking at a home near the University or Downtown segments, the heaviest work there is still ahead.
Project Connect and Austin Light Rail
The Austin Transit Partnership (ATP) is building Austin Light Rail Phase 1. Per ATP:
- Route: 9.8 miles of track from 38th Street on Guadalupe, through downtown, to South Congress and East Riverside, with 15 stops.
- Bridge: a new bridge across Lady Bird Lake with a path for pedestrians and cyclists.
- East Riverside: a new shaded pedestrian and cyclist path along the line, and a future extension to the airport.
- Frequency: its own dedicated railway, with trains every 5 to 10 minutes.
ATP’s timeline lists engineering, permitting, and preconstruction in 2026 to 2027, construction and testing from 2027 to 2033, and opening for service in 2033. ATP notes the schedule is for planning purposes and final dates depend on contractor input and the federal funding process. Its September 2026 status report says ATP has now awarded its major contracts, including a July 15 contract with Stadler US for light rail vehicles, as it moves toward construction in 2027.
For the exact stop locations, use ATP’s current map on its light rail page. Plans can be adjusted during design, so check the latest map rather than an older article.
Transit that runs today: the Red Line
CapMetro’s Red Line (Route 550) already runs 10 stations from Downtown to Leander, including Highland (ACC) and McKalla (Q2 Stadium). A standard single ride is $3.50, and CapMetro lists service every 15 to 30 minutes, with exceptions. Connector Route 466 runs from Kramer station to The Domain. CapMetro updated its weekday rail schedule effective October 12, so check the current timetable if you’re planning a commute around it.
What to check before buying near a corridor
Here’s what I’d look at for any home within a few blocks of I-35 or the light rail route:
- Your daily routes during construction. Look up the frontage roads, cross streets, and ramps you’d use. TxDOT posts I-35 closures on its project site.
- The schedule for the nearest segment. Use the table above to see when work is expected near the address.
- Noise and access. Visit at different times, including evenings, and note the construction activity.
- The plans for that block. Look at TxDOT’s segment schematics and ATP’s map to see what’s planned closest to the property.
- Disclosures and HOA documents. Read the seller’s disclosure and, for condos and HOAs, the association’s documents for any notices about nearby work.
- Flood maps. Drainage tunnels are part of the I-35 project, but they don’t change what today’s maps say about a home. My guide to checking flood risk covers that.
Questions to ask at a showing near a corridor
- Which I-35 segment or light rail stop is closest, and what does the latest schedule show for it?
- Has the seller received any notices about construction, right-of-way, or utility work nearby?
- For a condo or HOA, has the association discussed the projects, and is anything noted in its minutes or resale certificate?
- Which streets, ramps, or crossings would you use daily, and are any of them scheduled for closures?
- What does the property sound like on a weekday morning and a weeknight?
None of these questions has a right or wrong answer. They’re about knowing what you’re buying next to, so the construction years don’t catch you off guard.
Where to find official updates
- TxDOT I-35 Capital Express Central: segment schematics, the technical schedule, closures, and Community Connectors open-house meetings
- ATP’s project timeline and light rail map
- CapMetro Rail for Red Line schedules and fares
FAQ
TxDOT expects construction along the Central project corridor to be complete in 2033, weather permitting.
No. TxDOT says the project adds two non-tolled HOV managed lanes in each direction.
ATP’s timeline shows opening for service in 2033, with final dates depending on contractor input and federal funding.
I can’t predict that, and I’d be skeptical of anyone who says they can. Look at what’s planned near the home, how it fits your routes, and the home itself.
Browse the Downtown, East Austin, South Congress, Hyde Park, and The Domain guides, or read the buyer’s guide for the full process.
Looking at a home near I-35 or a planned stop? Book a free buyer consultation and we’ll pull up the plans for that block together.
Sources
- I-35 Capital Express Central Project, TxDOT (accessed Nov 17, 2026)
- CapEx Central Phasing technical schedule, TxDOT, last updated Sept 2, 2026 (accessed Nov 17, 2026)
- TxDOT breaks ground on transformational I-35 Capital Express Central project, TxDOT (accessed Nov 17, 2026)
- Light Rail, Austin Transit Partnership (accessed Nov 17, 2026)
- The Process, Austin Transit Partnership (accessed Nov 17, 2026)
- Project Connect Status Report, September 2026, Austin Transit Partnership, available from atptx.org (accessed Nov 17, 2026)
- CapMetro Rail, CapMetro (accessed Nov 17, 2026)